Seal Coat & Ditch Work Phase 1 Status update August 13, 2017


  • Road patching on all streets for the 2017 improvements is complete.  Some follow-up work will continue on Summit and Essex after further review with the engineering firm.
  • Additional storm water culverts/sewers and driveway culverts are complete.
  • Culvert work on Brandy is complete, some follow-up work will be required.
  • All ditch clearing is complete.
  • Shoulder repair and ditch reshaping will start on Tuesday, 8/15/2017
  • Culvert reinforcement on Stratford will start this week.
As a reminder, please keep vehicles out of the ditches on the streets listed below from 7 am to 6 pm, so work can be completed in a timely manner.
Road resurfacing is still planned for 2017, and will commence once the ditch work is complete.  Greenbriar was added to the resurfacing list for 2017.  Dates for this work will be posted soon.  During this time, do not park vehicles on the streets listed below from 7 am to 6 pm.
Ditch Repair Streets:
  • Summit Dr
  • Essex Dr
  • Raleigh Ave
  • Canterbury Rd
  • Sherry St
Road Resurfacing Streets:
  • Essex Dr
  • Canterbury Rd
  • Sherry St
  • Brandy Dr – between the lodge and Brandy Lane.
  • Raleigh Ave
  • Stratford Dr
  • Summit Dr
  • Roxbury Rd – North cul-de-sac only
  • Heritage Dr – starting at Thornton Dr and ending near 566 Heritage Dr.
  • Greenbriar Rd – Recently added